Verbal public comments may be submitted pursuant to the instructions noticed in the meeting agenda, which will be available at least 72 hours prior to the meeting at https://lossan.legistar.com/Calendar.aspx

File #: 17-376   
Type: Lossan Status: Agenda Ready - Regular Calendar
File created: 6/25/2019 In control: Board
On agenda: 7/15/2019 Final action: 7/15/2019
Title: Central Coast Layover Facility Expansion Project Funding Update
Sponsors: James D. Campbell
Attachments: 1. Staff Report

Title

Central Coast Layover Facility Expansion Project Funding Update

 

Overview

The Los Angeles - San Diego - San Luis Obispo Rail Corridor Agency assumed the lead agency responsibility for the Central Coast Layover Facility Project in May 2018, following the initial project definition and programming activities completed by the California Department of Transportation, Division of Rail and Mass Transportation. The project is fully funded through the State Transportation Improvement Program. In order to facilitate the appropriate environmental clearance document, additional time was requested from and denied by the California Transportation Commission. In order to preserve funding for this project, a funding request must be submitted for the 2020 State Transportation Improvement Program.

 

Recommendation(s)

A.                     Direct staff to continue the Project Approval and Environmental Documentation efforts for the Central Coast Layover Facility Expansion Project.

 

B.                     Authorize the Managing Director to submit a 2020 State Transportation Improvement Program funding request for preparing Plans, Specifications, and Estimates for the Central Coast Layover Facility Expansion Project and process all necessary agreements to facilitate the submission and acceptance of funds.